Supertech — Delay in possession and penalty charged

I have a booked a flat in supertech capetown in 2010, with number cmc 1301 and was supposed to get possession in april 2013.
After following up regularly for 2 years and escalating to the gm dinesh handa o i finally got the offer of possession in 13th april 2015.
The delay was of more than 2 years.
In the letter i was shocked to see a penalty of 3.13 lac.
I again wrote to dinesh handa who forwarded the same to customer support for resolution.
I contacted their customer support, wrote n number of emails but no one replied.
Finally i went to their office in noida. A customer care lady met me and after listening to be told me that nothing will be done.
I told her that there is a delay of 2 years from supertech side and i have paid rent of more than 5lac for the delay.
So if i have been late in arranging for loan initially even they have also taken 5 years for possession and that too after running after them. They were in no mood to give the possession offer.
I have emails which show followups on possession.
I even filed a complaint with credai, complaint number being 0615004120 on 13th june.
I received an email from credai on 24th august that my hearing will be on 5th september 2015.
I again wrote to supertech to resolve this amicably.
After many followups again i got an email from tanzeel ansari on 25/8/2015 assuring of resolution.
Then she called me on 1st september and told me that i should take back my case from credai as they have taken approvals and now i only needed to pay 31k and rest all is waived off.
I went to supreme court, consumer forum at the given date and time and took back my complaint.
Then i was called in supertech office for full and final settlement, i went and met customer service manager reena gulati who said that this was a simple case and if i had met her earlier she would have resolved it .
She gave me all the forms and made a calculation of dues including 31k of penalty.
I went again with filled up form and payment chq.
After few hours of waiting she came back and told me that this was a mistake and the amount is 1.80 lac.
I said this is cheating and i have even taken back my case from credai.
I again went back and rewrote to credai to open my case again.
I got an email from anitesh singh chauhan assuring me that he will resolve the issue urgently .
On 23rd jan 2016 he called me for a meeting.
To my disbelief he again told me the same thing which was told to be in september 2015 that i need to pay 1.80 lac.
I told him that you assured me of resolution and he said this is what they could do.
From september 2015 again till now march 2016 i am still running after them and since they are a big company they are thinking to bully customers and really think that they can get away with anything.
They have charged the penalty @ 24% per annum whereas given me a relief of only 5/- per sq. Feet.
Out of 3 lac they have only removed 1.20 lac and asking me to pay 1.80 lac which is a huge amount and i cannot pay.
I told them that if they had given the possession on time to me i would have paid the penalty without any issues but due to their delay i have also drained my 5 lac as rent and i cannot pay now 1.80 lac more.
Outocme required :so either they compensate me for the rent which i paid due to their delay which is 5lac and then i will pay the penalty of 1.80 lac or they remove the penalty accepting their delay too and will not drag this any further.
Below dates are of significance.
Flat booked : 19/10/2010
Possession date : april 2013
Grace period : october 2013
Possession follow up emails started on : 24/08/2014
Possession letter date : 13/04/2015
Complaint filed in credai : 13/06/2015
Email from tanzeel for resolution : 25/08/2015
Call from tanzeel for penalty waiver: 01/09/2015
Credai hearing date : 05/09/2015
Email to credai to reopen case : 27/09/2015
Email from anitesh singh chauhan assuring resolution : 22/01/2016
Meeting with anitesh at supertech office : 23/01/2016

1 thought on “Supertech — Delay in possession and penalty charged”

Leave a Comment

Your email address will not be published. Required fields are marked *

  1. I am also a victim of supertech. I received a demand letter two days back and shocked to see their calculations.

    Without bringing in our notice, the flat size is increased from original booking of 1010 sqft to 1106 sq ft , I compared the old floor plan with new one, no increase in carpet area, only two balconies are increased by 1ft. This is a clear case of fraud.

    There is a huge interest penalities imposed for delay of few months even for the periods when the farmer agitations were going on.

    Other charges , like water connection, farmer compensation, labor WELFARE are also there.

    I request all buyers facing such issues to come together and take the matter to appropriate authorities for resolution.

    Rgds.
    MMT

    [email protected]