Vatika Group – Claim for compensation for the delay caused.

Vatika Group Reviews & Complaints

Reported By: J S Ahuja

Contact information: Vatika Group

Dear sir,

We have booked a flat in vatika emilia floors in november 2009 and as per the buyer agreement the possession was to be handed over to us by november 2013 but it was delayed and was finally given on 11 september 2016. Thus a delay of 34 months.
In buyer agreement it is written to pay a compensation @ rs 5 per sq. Feet for the delay caused,
Calculation of claim
34 x 5 x 975 = rs 1, 65, 750

I request you to help us in claiming the compensation. Would be very thankful to you.

Jatinder singh ahuja
9971400123